Stoll Street Improvements

Improvements to Stoll Street are expected to commence Monday, July 31. The primary aspects of this project will be replacing asphalt driveway aprons with concrete, miscellaneous curb repairs, and finally milling and repaving Stoll Street between College Road and Prospect Street.  A fire hydrant and water valve will also be replaced as part of the project. This work be is expected to take approximately three weeks to complete.  The Borough would ask that you refrain from parking along Stoll Street between 7:00 am and 5:00 pm while this work is ongoing.

Driveways will be inaccessible until the concrete aprons cure which generally takes about three days.

The Borough Officials apologize for any inconvenience this may cause and hope the you agree that repairing to this road is worth this inconvenience.