Water System Infrastructure Update-6/22/18

Netcong Water Infrastructure Improvements
Schedule Update through July 6th 2018

  • Boil Water Advisory is still in place
  • 5 out of 28 hydrants installed
  • Water valve work is 75% complete
  • All water samples have come back good

Work Area: Bank St @ Jenny Lind
Wednesday 6/27/18- excavate and plate for 2 valve installations, hand out shut off notices for Thursday the 28th
Thursday 6/28/18- Install 2 new valves, backfill, and pave

Work Area: Each side of Mills Creek under Rt 80 Overpass
Friday 6/29/18- excavate and plate east bound side of Mills Creek for valve installation on 7-3-18
Monday 7/2/18- excavate and plate west bound side of Mills Creek for valve installation on 7-3-18, hand out water shut off notices for the 3rd
Tuesday 7/3/18- shut off water, install valves on each side of Mills Creek and backfill

Work Area: 24 Dell Ave and 64 Koclas Drive
Thursday 7/5/18- excavate and plate for hydrant installations at 24 Dell and 64 Koclas, hand out water shut off notices for the 6th
Friday 7/6/18- shut off water and install hydrants and valves to 24 Dell Ave and 64 Koclas, backfill and pave

*water service may be interrupted outside of the immediate work areas
*this is a working schedule and dates may be delayed by weather or unforeseen excavation issues