The project is 25% complete as of 6/8/18

Work Area:  Wiltop Rd, Oak St, Elm St

Friday 6/8/18- excavate 5 locations and plate for next day cut outs- hand out water shut off notices for Monday the 11th

Monday 6/11/18- shut off water and insert new valves at all 5 locations, turn water back on and check for leaks and re plate

Tuesday 6/12/18- backfill and pave excavation areas

 

Work Area:  North St and Barone St

Wednesday 6/13/18- excavate 4 locations and plate for next day cut outs- hand out water shut off notices for Thurs the 14th

Thursday 6/14/18- shut off water and insert new valves/hydrants in 4 locations, turn water back on and check for leaks and re plate

Friday 6/15/18- backfill and pave excavation areas

 

Work Area:   College Rd and Hillside Ave E and Hillside Ave W

Monday 6/18/18- excavate 4 to 5 locations and plate for next day cut outs- hand out water shut off notices for Tues 6/19/18

Tuesday 6/19/18- shut off water and insert new valves/hydrants in 4 to 5 locations, turn water back on and check for leaks and re plate

Wednesday 6/20/18 backfill and pave excavation areas

 

*water service may be interrupted outside of the immediate work areas

*this is a working schedule and dates may be delayed by weather or unforeseen excavation issues  